摘 要
聯(lián)合站的設(shè)計(jì)是以?xún)?chǔ)運(yùn)教研室下達(dá)的的任務(wù)書(shū)為依據(jù)完成的。該聯(lián)合站東西350米,南北250米,年處理量為270萬(wàn)噸,采用密閉流程。
站外來(lái)油經(jīng)三相分離器、加熱爐、油氣分離器、電脫水器、穩(wěn)定塔等首先進(jìn)行油、氣、水的分離,再經(jīng)外輸泵和計(jì)量間等向外輸送。站內(nèi)氣體直接送往氣體處理廠進(jìn)行處理。
站內(nèi)劃分為油罐區(qū),污水處理區(qū),工藝區(qū),配電區(qū),消防區(qū),輔助生產(chǎn)區(qū),設(shè)計(jì)時(shí)設(shè)計(jì)了有泵流程,同時(shí)也考慮了停電流程,即使故流程。
根據(jù)任務(wù)書(shū)所給的站處理量和各種設(shè)計(jì)參數(shù),首先初步選擇了各工藝段設(shè)備,接著確定了總平面布置和聯(lián)合站的工藝流程。與此同時(shí),完成了平面布置圖和流程圖,設(shè)計(jì)并畫(huà)了泵房的管線安裝圖。
關(guān)鍵詞:聯(lián)合站;分離;生產(chǎn)流程;設(shè)備
ABSTRACT
The design of WH Central Treating Station was complicated according to the assignment given by the Storage and Transportation Teaching and Researching Department. It is 250 meters long from north to south and 350meters wide from east to west. The treating capacity of the station is about 2,700, 000 tons per year.
The central treating station treats well stream. Its main task is oil, gas and water separation. Gas, crude oil and water mixture flow into the central treating station. First, it goes into three phase separators, then goes through fluid jacket heaters, Two phase separators, electronic dehydrators, stabilization tower ,at last treated crude oil is pumped to the mineral terminal.
The central treating station includes two main processes, they are tight flow process with and without pumps. In addition, the accidental process while power is off was considered.
In the design, we considered the conditions given by the assignment; seclected and checked the equipments and pipelines.The design include three draws.
keyword:central treating station;separate;process;equipment